Grain Drying Complex Project

Customer Yarkovskaya Agricultural Cooperative
Object address Yarki, Voronezh Region, Russian Federation
Power 100 t/h
Design period
95 working days
Request a consultation

Stages
of design

1.
Engineering surveys
30 days
2.
Project documentation
35 days
3.
Non-governmental expertise
30 days

Equipment

ПОЛЫМЯ
AG ROSTROY
Scale 50%

Our project team

Our team includes professionals with over 20 years of experience in construction management and supervision. We not only calculate structures and units, we know how the construction process actually takes place, how to do it conveniently and quickly not only on drawings, but also on the construction site.
Chief Engineer
of the project
Design
engineer
Design
engineers
Design engineers
of engineering networks and systems

Similar completed projects